标题:Modeling study on the influence of the strip filling mining sequence on mining-induced failure
作者:Jiang, Ning; Wang, Changxiang; Pan, Haiyang; Yin, Dawei; Ma, Junbiao
作者机构:[Jiang, Ning; Wang, Changxiang; Pan, Haiyang; Yin, Dawei; Ma, Junbiao] Shandong Univ Sci & Technol, State Key Lab Min Disaster Prevent & Control Shan, 更多
通讯作者:Wang, CX;Wang, CX
通讯作者地址:[Wang, CX]Shandong Univ Sci & Technol, State Key Lab Min Disaster Prevent & Control Shan, Qingdao 266590, Peoples R China;[Wang, CX]Shandong Univ Sci 更多
来源:ENERGY SCIENCE & ENGINEERING
DOI:10.1002/ese3.660
关键词:3U coal seam mining; mining and filling sequence; proportioning; experiment; surface subsidence
摘要:The strip filling mining method can solve the problems related to mining under structures, under aquifers, and under infrastructure (3U coal seams), while the reasonable selection of the mining and filling sequence still requires further investigation. The current study was conducted to investigate the stress and surface subsidence of a filling body (or coal pillar) under two filling sequences through theoretical analysis, similar simulation tests, and numerical simulations. To achieve optimal filling materials for the Liudong Coal Mine, a low-strength similar paste filling material composed of fly ash, gypsum, and sand was developed. The relationships between the strength and the cement ratio and between the strength and the sand-binder ratio were discussed. Similar simulation tests showed that mining scheme 1 (mining before filling) could lead to the formation of an isolated island coal pillar in the mining process, mining scheme 2 (filling before mining) had less influence on surface subsidence, and the stress on the filling body was smaller for scheme 2 than for scheme 1. The distributions of the stress and plastic zone in the two different mining and filling sequences were obtained through numerical simulations. The method of first filling and then mining could greatly reduce the stress concentration and plastic zone during the mining process. In summary, mining scheme 2 (filling before mining) can avoid the formation of isolated island coal pillars in the process of mining, and without considering other factors, scheme 2 should be adopted as much as possible.